Notes:
·
Please
use caution when driving through work zones- 45 mph Thank you
· Upon completion,
· Please feel free to contact Commissioner
Valerie Covey’s office with questions or concerns you may have at 943-3370 or
comm3@wilco.org
· Rain has slowed progress on some work
items in the past few weeks
Progress on last week’s schedule:
·
Waterline
crew installed waterline along South Right of Way
·
Worked
on waterline bore crossing at Lakewood Drive South-west
·
Worked
on returning waterline easement to original condition
·
Prepared
subgrade from FM 3405 to
·
Continued
work on Traffic Signals at Woodlake and Del Webb intersections
·
Continue
to transfer water services from old to new waterline working east to Sedro
Work scheduled for this week:
·
Waterline
crew will continue waterline installation along South Right of Way
Rocksaws
excavating ahead of installation various locations
·
Work
on waterline bore crossings: Woodlake
·
Work
to return waterline easement to original condition
·
Install
new storm sewer pipe across Old Oak.
After the new pipe is installed, the ditchlines will be cut to the final
design
Subgrade
preparation to continue from FM 3405 working along both sides of the roadway
·
Continue
work on Traffic Signals Foundations at Del Webb, Woodlake intersections
General Notes:
·
During
the transfer of water services from the old to the new waterline, the water
will need to be shut off for about 30 minutes for residential and small
business customers. Customers will be
notified by the contractor, J C Evans, when this occurs. Water service switches for larger customers
will be done at night and the customers will be notified by
·
Several
organizations located along
·
J C
Evans is working on Sundays to take advantage of dry conditions whenever
possible
Utility Update
·
PEC -
is substantially complete. PEC is currently preparing documents for landowner’s
signature. As soon as the documents are signed the two poles will be installed.
·
Suddenlink
- is substantially complete. They are waiting on PEC to finalize their
relocation efforts and Verizon to removing their existing facilities prior to
completing their relocation efforts from Jim Hogg to FM 3405.
·
Verizon
- has begun to remove their existing facilities from Wildwood to Sedro
Trail. The remainder of Verizon's relocation work continues to be drastically
effected by the weather.
·
Atmos
- Complete