2024 Bond Project Updates
Project Updates
Summer Projects 2025:
Bond 2024
· EVHS – Corridor flooring replacement and wall painting
· GHS – Security gates and select fencing
· Forbes MS - Corridor flooring replacement and wall painting
· Cooper ES – Playscape equipment replacement and playscape surface replacement.
· Cooper ES - Corridor flooring replacement and select wall painting
· Cooper ES – Fire Alarm Replacement
· Ford ES – Fire Alarm Replacement
· Village ES - Corridor flooring replacement and wall painting
· Mitchell ES - Corridor flooring replacement and select wall painting
· Multiple Campuses - Shatter resistant window film
· Multiple Campuses – gate hardware and security fencing installation
Elementary 12 and Middle School 5:
Contractor: American Constructors
Sitework for underground utilities, roads, parking areas, and building pads is ongoing. Pier drilling for the foundation system will begin during the month of December. These campuses will be ready for students in August 2026.
Drone View of ES12 & MS5:
New Frost ES:
Contractor: Bartlett Cocke General Contractors
This project started on June 24, 2024. This project is scheduled to be completed in late June 2025 and ready for students in August 2025.
High School #4:
Contractor: Bartlett Cocke
Permits from the City of Georgetown (CoG) and the Texas Commission for Environmental Quality (TCEQ) were received on 4/11. Onsite activities for this project started on 4/15. Delivery of this project is scheduled for May 2028.
Elementary 12 and Middle School 5:
Contractor: American Constructors
Sitework for underground utilities, roads, parking areas, and building pads is ongoing. Pier drilling for the foundation system will begin during the month of December. These campuses will be ready for students in August 2026.
Drone View of ES12 & MS5:
New Frost ES:
Contractor: Bartlett Cocke General Contractors
This project started on June 24, 2024. This project is scheduled to be completed in late June 2025 and ready for students in August 2025.
High School #4:
Contractor: Bartlett Cocke General Contractors
Delivery of this project is scheduled for May 2028.
The next images are renderings of this project. These images reflect the concept of this project and may not reflect the finished product. The logo’s, mascots and school colors seen in these images are placeholders only.
Main Entrance:
View from Stadium bleachers:
View of Cafeteria Dining Hall
Elementary 12 and Middle School 5:
Contractor: American Constructors
Sitework for underground utilities, roads, parking areas, and building pads is ongoing. Pier drilling for the foundation system will begin during the month of December. These campuses will be ready for students in August 2026.
Drone View of ES12 :
Drone View of MS5:
New Frost ES:
Contractor: Bartlett Cocke General Contractors
This project started on June 24, 2024. This project is scheduled to be completed in late June 2025 and ready for students in August 2025.
East View High School Performing Art Center Project and Field House Additions:
Contractor: American Constructors
The images below are early concept renderings of how the new performing arts center at EVHS could look. These images are not representative of the finished product as we are currently in the midst of design, but gives the viewer a glimpse of the potential impact a project like this will have on the identity of this campus.
Elementary 12 and Middle School 5:
Contractor: American Constructors
Sitework for underground utilities, roads, parking areas, and building pads is ongoing. Pier drilling for the foundation system will begin during the month of December. These campuses will be ready for students in August 2026.
Drone View of ES12 & MS5:
New Frost ES:
Contractor: Bartlett Cocke General Contractors
This project started on June 24, 2024. This project is scheduled to be completed in late June 2025 and ready for students in August 2025.
New Frost ES Drone Image:
Elementary 12 and Middle School 5:
Contractor: American Constructors
Sitework for underground utilities, roads, parking areas, and building pads is ongoing. Pier drilling for the foundation system will begin during the month of December. These campuses will be ready for students in August 2026. A groundbreaking ceremony is being coordinated and scheduled for May 9.
Drone View of ES12 & MS5:
New Frost ES:
Contractor: Bartlett Cocke General Contractors
This project started on June 24, 2024. This project is scheduled to be completed in late June 2025 and ready for students in August 2025.
High School #4:
Contractor: Bartlett Cocke
Delivery of this project is scheduled for May 2028.
The next four images are renderings of this project. These images reflect the concept of this project and may not reflect the finished product. The logo’s, mascots and school colors seen in these images are placeholders only.
Main Entrance
View from Stadium bleachers:
View of Cafeteria Dining Hall