Skip To Main Content

2024 Bond Project Updates

Project Updates

Georgetown ISD Construction

Elementary 12 and Middle School 5:

Contractor: American Constructors

Sitework for underground utilities, roads, parking areas, and building pads is ongoing. Pier drilling for the foundation system will begin during the month of December. These campuses will be ready for students in August 2026.       

Drone View of ES12 & MS5

New Frost ES:

Contractor: Bartlett Cocke General Contractors

This project started on June 24, 2024. Interior topping slab at gym is being prepared for an upcoming concrete pour.  Drywall is being installed and new rooftop HVAC equipment is being set in place. Site work for new parking lots and driveways is ongoing as well. This project is scheduled to be complete in late June 2025 and ready for students in August 2025.

Drone View of Frost ES